Oshkosh Corporation
Faith Technologies provided all of the electrical and fire alarm installation for Oshkosh Truck Corporation’s data center.
Data centers are very densely populated with electrical and mechanical systems, so up front MEP coordination was essential. Faith Technologies utilized its project preplanning process to ensure that all MEP coordination was done prior to underground conduit installation. We avoided conflicts with mechanical and other systems by detailing all of the conduit runs and equipment locations prior to start of construction, and worked closely with the construction manager to identify the exact dimensions of their furnished equipment so that conduit stub ups were placed in the exact location or equipment compartment required.
In the end, this project was completed successfully on time and under budget.
PROJECT OVERVIEW
Location
Menasha, WI
Size
35,000 square feet